Construction Project
BMW Car Factory Leipzig, Car Body Construction |
Location
- Industrial Park Leipzig-North
|
Client
|
Planning
- ARGE overall planning with the participation of IFB Dr. Braschel AG and WPW Ingenieure, Leipzig
|
Investment volume
|
Construction period
- December 2002 to February 2004
|
Contracted services for BMG
- Section 15.8-9 HOAI-Property planning for buildings
- Section 57 HOAI-Local construction supervision
- Construction site logistics
|
Lot area
|
Footprint
|
Gross floor space
|
Gross volume
|
Storeys
- Two-to Four-storey factory, in part with basement rooms and escape tunnel, installation of two conveyor levels made of steel and other production installations
|
Utilization
- Factory for construction of car bodies
|
Construction
- Construction on concrete foundations, steel construction and steel with reinforced concrete composite construction, façade as insulated aluminium composite construction, roof with insulated trapezoidal sheet metal covering, installations in reinforced concrete
|
Design/Fixtures
- Factory with functionally oriented equipment in production, toilets, offices and ancillary systems, factory floor with magnesia coating
|